1.3 Overview
The UPS provides two power paths between the utility source and the critical load.
Figure 1.1 shows the path for normal operation, with the load powered from the inverter.
Figure 1.2 shows the path for bypass operation, with the load supplied through the static
bypass line.
Figure 1.3 shows the path for battery operation, with the load supplied from the inverter.
A) Normal Operation.
FIGURE 1.1 Single Line Diagram - Normal Operation. Load powered by inverter
During normal operation, the path through the inverter is used to power the load.
Referring to Figure 1.1: Input AC power is converted to DC by the Converter. DC power is
utilized to charge the UPS battery and to provide power to the Inverter. The Inverter
converts the DC power to clean AC power to supply the critical load.
The conversion - inversion process eliminates any voltage transients or fluctuations
existing in the input power before it reaches the critical load.
* The AC Bypass Input circuit breaker (MCCB) for protection of the UPS and cables are field
supplied and field installed. (See WARNING 2 on page 1-2)
UPS Module
Power Flow
Not in Use
AC input
CB
FB
72B
52RS
CONVERTER
INVERTER
Output
52C
52RC
FI
FO
BATTERY
User
su
pp
lied
52CS
Maintenance
Bypass
Switch
50kVA, 80kVA:
External Battery
Static Transfer
Switch
CB
AC Bypass
In
put