Powerware IPK-0319 Network Card User Manual


 
UPS Power Management
22
BestLink SNMP/WEB Adapter User’s Guide : LTM-1343 B Draft 10/03/2001
3. If you entered a host name for the Mail Server, you must enter the IP
address of your network DNS Server in the
DNS Address block.
4. To receive a daily status report, enter the time of day to send the
e-mail (in 24-hour format).
5. Enter the
Mail Account, Description, Mail Type, Event Level,andEvent
Type
for each recipient. Refer to the online help file for more details
on each of these fields.
6. Select
Set Values to save your changes.
Performing a Manual UPS Battery Test
You can use the BestLink Adapter to manually perform a UPS battery test. The
ability to test the UPS is model dependent, so consult your UPS
documentation for more information.
1. To manually start a battery test on a specific UPS, select
Control from
the menu at the top of the home page.
2. Become a Superuser and then select
Initiate Battery Test, followed by
Set Values to start the process.
3. To stop the test while in progress, you can select
Cancel Battery Test
followed by Set Values.
Scheduling a UPS Battery Test
You can use the BestLink Adapter to perform a UPS battery test on a
user-defined schedule.
1. To schedule a battery test on a specific UPS, select
Control from the
menu at the top of the home page.
2. Select
Battery Test Schedule.
3. Become a Superuser and then select the
Test Day and Test Time (in
24-hour format) for the test to be initiated by the BestLink Adapter.
The test is performed each week on the specified day and time until
the
Test Day is changed to Disabled.
4. Set
Set Values to update the adapter with the schedule information.