2.1 Introduction
MBE is delivered completely assembled. For instructions on installation of a single
unit or two units in a 19-inch rack refer to the Rack Mounting Kit for 19-inch Racks
guide that comes with the RM kit.
After installing the unit, see Chapter 3, Operation for operating instructions.
In case a problem is encountered, refer to Chapter 4 for fault isolation and
troubleshooting instructions.
Any adjustments, maintenance or repairs should be performed only by a skilled
technician who is aware of the hazards involved.
Always observe standard safety precautions during installation, operation, and
maintenance of this product.
2.2 Site Requirements and Prerequisites
Inspect the equipment container before unpacking. Note and report evidence of
damage immediately to your RAD distributor.
Install the MBE unit within 1.5m (5 ft) of a grounded AC outlet furnishing
240V (115V).
Allow at least 90 cm (36") of frontal clearance for operator access. Allow at least
10 cm (4") clearance at the rear of the unit for interface cable connections.
The ambient temperature should be regulated between 0° to 50°C
(32°F to 122°F) at a relative humidity of up to 90%, non-condensing.