Chapter 3: 6C105 Setup
3-4 6C105 Overview and Setup Guide
3.2.3 Rack Mounting the 6C105
The 6C105 can be mounted in a standard 19-inch equipment rack.
Two people may be required to lift the chassis into place.
The chassis is secured with ten screws, five on each side. Using the screws
provided with the equipment rack, secure the 6C105 to the rack, starting
with the bottom holes and working up, as shown in Figure 3-2.
Figure 3-2 Rack Mounting the 6C105
!
CAUTION
If the rack is not secured to the floor, it is recommended that
the chassis be installed in the bottom half of the rack. This
prevents the rack from being top heavy.
!
CAUTION
Read Chapter 2 in this manual before completing the following
procedure.
Rack Mounting
Screws (5)
Rack Mounting
Screws (5)
Rack Mounting
Holes (5)
Rack Mounting
Holes (5)