Unpacking the UPS and Site Preparation
6
2.0 UNPACKING THE UPS AND SITE PREPARATION
2.1 Inspection
Upon receiving your Liebert
®
GXT3-10000T220
™
, examine the packaging for any signs of
mishandling or damage. While removing shipping materials, inspect the UPS for damage. If any
damage is noted, notify your local Liebert representative and your carrier.
2.2 Required Setup Equipment
The following tools are required to set up your Liebert GXT3-10000T220:
•pallet jack
• utility knife or scissors
• screwdrivers—Phillips and straight blade
2.3 Unpacking
Exercise care when removing the packaging to avoid damaging the UPS. Check all packaging to
ensure that no items are discarded. Remove the packaging following the sequence in Figure 3.
1. Using a pallet jack, move the Liebert GXT3-10000T220 near its installation site.
2. Unlock all the snaps securing the shipping case to the shipping pallet.
3. Lift the shipping case off the UPS.
4. Remove the EPE packing cushions from around the Liebert GXT3-10000T220.
5. Remove the ramp from the front and slip into the slot on the front of the shipping pallet.
6. Roll the UPS off the shipping pallet.
Figure 3 Unpacking
Storage
If the UPS will be stored, it must be placed indoors in a clean, dry area. Protect all the equipment,
including its batteries, from extreme temperatures, high humidity, spills and other damaging
conditions. Refer to Table 9 for permissible environmental conditions for storage.
Handling
The equipment must be kept upright at all times and handled with care. It may be damaged if
dropped or subjected to severe impact.
!
WARNING
The UPS is heavy and will roll when on an incline. When removing the unit from its shipping
pallet, use at least two persons.
Unlock
Plywood
Case
Ramp
Packing Cushion
(EPE)
Ramp in slot
on shipping pallet
GXT3 T220
UPS