Liebert NfinityTM Power Supply User Manual


 
Installation
8
2.0 INSTALLATION
2.1 Inspection
Upon receiving the UPS, examine the packaging for any signs of mishandling or damage. If any dam-
age is noted, call your local dealer or Liebert representative and/or notify your carrier.
2.1.1 Environment
2.1.2 Required Setup Equipment
The tools below are required to properly set up your UPS:
Pallet jack
1/2" (13mm) ratchet or wrench
Torque wrench (in-lb)
Flathead screwdriver
#2 Phillips screwdriver
2.1.3 Site Preparation
When deciding where to locate your UPS,
consider the weight and size of the unit. Make
sure that the structural integrity of the floor
can withstand the weight of a fully loaded unit.
Check to make sure that your UPS will be
located in a well-ventilated area with at least
12 inches (305mm) behind it. The UPS is
air-cooled utilizing internal fans. Air is drawn
into the front of the UPS and is exhausted
through ventilation grilles in the back. It should
also have at least 36 inches (915mm) in front in
order to change modules when necessary.
The unit frame is bolted to the shipping pallet to ensure safety. It is recommended that a pallet jack
be used to transport the unit to its operating location (prior to unbolting the unit).
NOTE
Operating in temperatures above 77°F (25°C) will reduce battery life. The UPS environment
must be free of conductive contaminants and excessive moisture (water and condensation),
flammable vapors, chemical fumes, corrosive gases and liquids.
36"
(915 mm)
12"
(305mm)