PREINSTALLATION
Installation responsibilities
The following explains Xerox and customer responsibilities.
Table 1-20. Installation responsibilities
Xerox • Install the hardware component of the XPMF/VMS interface.
• Assist you, if necessary, in installing the software
component.
• Provide the XPMF/VMS interconnect kit.
Customer
• Arrange for telephone lines and modems to be installed, if
required by your interconnect configuration.
• Verify kit contents to make sure all necessary items are
included.
• Install the host-resident software component (part of the
XPMF/VMS kit provided by Xerox) onto the VMS system.
• Obtain all necessary hardware and software to form the
selected connection solution.
• Coordinate the installation steps that involve both DEC and
Xerox service organizations.
• Produce specifications for XPMF/VMS during the
configuration of the printer.
• Install any communications controller components needed
for the DEC VAX system that submits jobs to the LPS.
Installation requirements
Before installing the host-resident software, you must have the
following privileges and resources available:
• SETPRV privilege, or CMKRNL, WORLD, and SYSPRV
privileges
• Minimum of 1,000 blocks of free disk space during
installation; 500 blocks after installation.
Hardware requirements
Listed below are the three VAX/VMS systems that support the
VAX-resident print supervisor (symbiont) software and the
requirements for each.
Note: Appropriate communication cables and modems may be
required. Consult your sales representative.
XEROX 4050/4090/4450/4650 LPS INSTALLATION PLANNING 1-25