4. Place the fuse platform in the specified mounting space within the rack.
5. Secure the fuse platform to the equipment rack as shown in Figure 14 using the four 3/8-
inch (9.53 mm) long pan-head screws and flat washers provided.
Figure 14. Mounting Fuse Platform on Rack
4.3 Grounding Chassis
Use the following procedure to connect the panel to an approved office ground source:
1. Obtain two lengths of #10 AWG wire for use as the chassis grounding wires.
2. Terminate one end of each wire with the #10 ring terminals provided (requires crimper).
Caution: Do not use any hardware other than the hardware supplied with the fuse platform.
Note: A single ground wire can also be used. If using a single ground wire, use #6 AWG
wire terminated at either stud.
18865-A
DETAIL DRAWING OF
MOUNTING SCREWS
AND WASHERS
USE #12 STAR WASHERS INSTEAD OF FLAT
WASHERS IF REQUIRED BY LOCAL PRACTICE
TIGHTEN MOUNTING SCREWS
TO 27 POUND-FORCE INCHES
(3.1 NEWTON METERS) OF TORQUE