INSTALLATION
Eaton
®
9130 UPS (700–3000 VA) User's Guide S 164201718 Rev 2 www.powerware.com
25
Up to 1500 VA Models 2000–3000 VA Models
Figure 10. Connecting the UPS Internal Batteries
3. If you are installing EBMs, see the following section, “Connecting
the EBM(s),” before continuing with the UPS installation.
4. Replace the UPS right front cover.
To replace the cover, verify that the ribbon cable is protected and (if
EBMs are installed) the EBM cable is routed through the knockout
on the bottom of the cover. Slide the cover to the left until it aligns
with the left front cover. Reinstall the two screws on the right side
of the right front cover.
5. If you are installing power management software, connect your
computer to one of the communication ports or optional
connectivity card (see page 53). For the communication ports, use
an appropriate cable (not supplied).
6. If your rack has conductors for grounding or bonding of ungrounded
metal parts, connect the ground cable (not supplied) to the ground
bonding screw. See “Rear Panels” on page 91 for the location of
the ground bonding screw for each model.
7. If an emergency power-off (disconnect) switch is required by local
codes, see “Remote Emergency Power-off” (REPO) on page 56 to
install the REPO switch before powering on the UPS.
8. Continue to “UPS Initial Startup” on page 34.