Powering on sequence
1 Power on of all the server UPS units
2 Server startup
The server OS startup is suspended until the ETERNUS DX Disk storage system startup is complete
(*1).
3 Issuance of command to turn on the ETERNUS DX Disk storage system from the power synchronized
unit
4 ETERNUS DX Disk storage system startup
*1: The server must be set to suspend server OS startup until the ETERNUS DX Disk storage system startup is
complete.
Powering off sequence
1 Shutdown of all the servers
2 Shutdown of all the server UPS units
3 Issuance of command to turn off the ETERNUS DX Disk storage system from the power synchronized
unit
4 ETERNUS DX Disk storage system shutdown