Fujitsu RX600 S5 Server User Manual


 
RX600 S5 Operating Manual 51
Hardware installation Rack installation/removal of server
V CAUTION!
Ensure that the safety lock has been inserted before the server is
inserted (see figure 4 on page 48).
V CAUTION!
At least two people are needed to position the server in the rack.
(For the Japanese market, please refer to " 安全上の注意およびその他の
重要情報 ".)
Ê Extend the telescopic rails completely to the front (1).
I They must click into place so that they can no longer be moved.
Ê Lower the server from above onto the projecting telescopic rails (2), (3). As
you do this, the locking bar (4) engages.
Ê Push the locking mechanism of both telescopic rails up (5).
Ê Push the server as far as it will go into the rack (6).
Ê Fasten the server to the rack (7) using the two knurled screws (front panel).
Torque: 0.25 Nm
Ê Route the cables as described in the Technical Manual for the rack in
question with the server pushed in.
4.2.3 Installation in 3rd party racks
I The support systems from Fujitsu are suitable for use in any 3rd party
racks for standard servers (installation depth 714 - 785 mm) without
restrictions.
Ê Refer to the manual from the rack manufacturer for details of the mechanical
installation and the climatic conditions.
V CAUTION!
When installing in 3rd party racks, it must be ensured that an air flow
from the front to the back of the rack is guaranteed.
Ê Fit the required original parts (support bracket or cable management
system).