HP (Hewlett-Packard) DL980 G7 Server User Manual


 
Hardware options installation 53
4.
Connect the power cord to the power source.
5. Be sure that the power supply LED is green ("Power supply LED" on page 13).
6. Be sure that the front panel external health LED is green ("Front panel LEDs" on page 8).
Internal solid state drive expansion bay option
1. Power down the server (on page 22).
2. Extend the server from the rack (on page 22).
3. Remove the access panel (on page 23).
4. Remove the SPI board.
5. Install the solid state drive.
6. Connect the cable.
The cable and the cable arrangement might appear differently from shown.