HP (Hewlett-Packard) ML110 G6 Server User Manual


 
Hardware options installation 30
1.
Power down the server (on page 7).
2. For ML110 G6 servers, extend the server from the rack.
3. For ML150 G6 servers, do one of the following:
o Unlock and remove the bezel ("Remove the tower bezel (ML150 G6 servers)" on page 8).
o Extend the server from the rack.
4. Remove the access panel (on page 7).
5. Remove the air baffle.
For more information, see the server installation sheet on the HP website
(http://www.hp.com/go/bizsupport).
6. Open the DIMM slot latches.
7. Install the DIMM.
8. Install the air baffle.
9. Install the access panel.
10. For ML110 G6 servers, slide the server back into the rack.
11. For ML150 G6 servers, do one of the following:
o Close or install the tower bezel, as needed.
o Slide the server back into the rack.
If you are installing DIMMs in lock-step configuration, configure this mode in RBSU ("ROM-Based Setup
Utility" on page 38).
For more information about LEDs and troubleshooting failed DIMMs, see the server installation sheet on the
HP website (http://www.hp.com/go/bizsupport).
Battery-backed write cache battery pack option
CAUTION: To prevent a server malfunction or damage to the equipment, do not add or remove
the battery pack while an array capacity expansion, RAID level migration, or stripe size migration
is in progress.