Installation and User Manual
3.1.3 Post Start Up Safety Check List
After initial start-up of the system, normal operation should be tested. At the minimum, the following tests should
be performed as applicable to your installation.
◗ Emergency power off (EPO) test.
◗ Remote emergency power off (REPO) test (if applicable).
◗ Inverter start and stop.
◗ Battery transfer test.
◗ Maintenance bypass procedure.
CAUTION
As soon as AC input power is supplied to the Galaxy 3000
(customer supplied upstream circuit breaker is in the "ON"
position), the load is initially supplied via the "Static Switch."
Verify that no error indications are present on the operator
interface panel.
3.1.4 Normal Shutdown Procedure
1. Press the gray (inverter off) button. The display will show “Confirm UPS Shutdown”. Toggle the up and down
scroll arrows button to “Yes” and press the return or enter button.The Yellow LED will turn on.
2. The UPS is now feeding the load from the static switch.
3. Open battery circuit breaker CB1, or QF1 (older UPS).
4. Rotate SR1 switch to bypass position.
5. At this point, the UPS is completely down, and the load is being protected through maintenance bypass.
6. To power down the load, open the upstream circuit breaker(s) which feed the UPS.
Operation 3 —3
86-172010-00 C05