Quick Start
Getting Started with Galaxy 3000
System Setup describes receiving and handling of the Galaxy 3000, a description of major components, the battery
cabinet, and definition of the control panel indicators, which includes electrical, mechanical and environmental
specifications.
MGE also recommends obtaining an MGE field service engineer for final installation and basic startup for single and
parallel units.
CAUTION
Scheduling of the MGE Field Service Engineers typically should be
done 7 to 10 days before they are required on-site. If the startup
of the UPS is critical to maintaining your schedule, please call the
MGE toll free telephone number at
1-800-438-7373 for assistance.
The MGE Field Service Engineers will
insure a quick installation
for the initial safe startup and configuration of your Galaxy 3000.
Final installation and start-up should be completed by a qualified MGE Field Service Engineer.
First steps by an on-site qualified Technical Engineer
Step 1. Unpack and position the unit.
Step 2. Connect the main (utility) power.
Step 3. Connect the output to the power distribution panel.
Final steps by MGE Field Service Engineer
Step 4. Call MGE and wait for the MGE Field Service Engineer to complete the installation.
Step 5. The MGE Field Service Engineer finalizes installation and the startup process.
Optional: Procedure for temporary power prior to the final startup.
Required Equipment and Tools
The following equipment and tools are recommended for on-site installation:
◗ Digital volt meter (DVM)
◗ 1/8 inch slotted screwdriver
◗ Pallet jack/forklift
◗ Conduit installation tools
◗ Nut driver set
Quick Start QS—1