2.0 Uncrating/Inspection/Storage/Disposal
2.1 Uncrating the new UPS equipment 15/25/30/33kVA:
Upon receipt of the UPS, a careful inspection for shipping damage should be made. Units
shipped within North America are shrink-wrapped, those outside North America are crated.
1. Remove packing material.
1a. For international units, remove
the screws that attach the
shipping crate to the pallet.
Remove the crate and foam
packing material.
2. Unbolt the rails from both the unit and
the shipping pallet. Place the rails on
the front of the pallet. Use the four
½x3” bolts to secure the rails to the
shipping pallet. Attach the rails as
shown to the front of the pallet.
3. Place the tie brackets in the slots at the lower
end of the ramps. SLOWLY roll the unit
down the ramp.
DANGER
TOP HEAVY EQUIPMENT. IMPROPER LIFTING CAN RESULT IN INJURY OR
DEATH. LIFT AND MOVE CAREFULLY AND ONLY WITH ADEQUATE
EQUIPMENT AND TRAINED PERSONNEL. THIS EQUIPMENT WILL TIP OVER
EASILY UNTIL FIXED IN PLACE.