American Power Conversion MX28B2400+27V Power Supply User Manual


 
MX28B-1200+27V PRODUCT MANUAL Rev 1
24
5.10.3 Full System Power Up
To complete a full system power up, perform the following steps
1) Turn OFF all the circuit breakers that supply AC power to the rectifiers in the MX28B DC
power plant.
2) Turn on the external circuit breaker from the battery to the power plant.
3) Turn on all the circuit breakers that supply AC power to the rectifiers in the MX28B DC
power plant.
4) Load circuit breakers may now be turned on and inserted as required.