Final Mechanical Installation
Connect Battery Securing Brackets for Stability
Caution: Wait until the system is ready to be powered up before installing batteries.
Failure to do so can result in a deep discharge of the batteries and cause permanent damage
(the time from the battery installation time till the UPS is powered up should not exceed
72 hours or 3 days).
Note: The battery securing brackets are only used in non-seismic areas for stability, and
when seismic battery locks are not part of the installation.
1. Install the batteries by pushing them all the way into the enclosure.
2. If required, install the battery securing brackets (A) to hold the batteries rmly in place. NOTE:
Do not install the brackets the same way they were positioned when the enclosure arrived. Rotate
the brackets 180° and reinstall.
Note: Battery securing brackets are delivered with the UPS and XR Battery Enclosure and
installed in front of the batteries. Battery securing brackets for additional batteries can be
purchased. Refer to option SUVTOPT003: APC Smart-UPS VT Battery Lock Kit for one
Battery Module (two batteries).