Liebert UPS System Power Supply User Manual


 
Chapter 9 Optional Parts
103
4 fixing holes
4 levelling bolts
4 fixing holes
4 levelling bolts
Fig. 9-2 Positions of leveling feet of battery cabinet
9.2.2 Installation of battery cabinet
The requirements for the locations of battery cabinet are the same with those of
UPS cabinet, so are the installation and fixing methods. Install the cabinet with
reference to the Fig. 9-1 and 9-2 and Fig. 2-5.
The battery cabinet exerts its weight on the floor through four leveling bolts(40mm
diameter). If the load bearing capacity of the floor is inadequate, add auxiliary
equipment to distribute the weight over a larger area, such as a big iron sheet or
increasing the number of supporting castor wheels.
The cabinet has flexible top and bottom cable access mode.
9.2.3 Wiring of the batteries
The front and back door, the cover board and each separation board should be
removed when installing the batteries. The installation should start from bottom to
up. The battery terminal should be bound with insulation tape after finishing the
wiring.
Fig. 9-3 shows the layout of the battery with the UF-B0100-30 battery cabinet as an
example. The installation of UF-B0065-30 is the same with UF-B0100-30, the
following contents may not be suitable for installation if different batteries are used
because the direction and wiring method of the battery are different.