Liebert UPS System Power Supply User Manual


 
Chapter 2 Cabinet Installation
16
2.4 Transportation
1. Hoisting the UPS
Prepare four cables of length 1.5 m and the weight bearing capacity of each cable
of 1.5 tons. The UPS has four lifting rings and should be installed at the top of the
UPS
2. Transportatio with Forklift
The UPS can be raised by forklift in four directions – front, back, left and right. But
the transportation distance should not exceed 10 m.
2.5 Positioning of UPS
The UPS cabinet exerts its weight on the floor through four castors. If the load
bearing capacity of the floor is inadequate, add auxiliary equipment to distribute
the weight over a larger area, such as a big iron sheet or increasing the number of
supporting castor wheels.
Note
As the UPS is cooled from the bottom, at least 10 cm space should be left at the
bottom of the UPS for ventilation
There are three kinds of positioning methods:
1. Non-Fixed position
Place the UPS directly on the flat ground . The ground should be made of Industrial
cement. Level the UPS by lowering and adjusting the leveling bolt at the base of
the UPS.
4 M20 screws for
levelling feet
Figure 2-5