![](http://pdfasset.owneriq.net/2/67/267d70bd-043d-45a3-80bb-27b95e0d4ad8/267d70bd-043d-45a3-80bb-27b95e0d4ad8-bg19.png)
Chapter 1 17
Introduction and Installation
Installation
Step 5. Activate the Test Set
1. Connect the semi-rigid cables that were shipped with your test set as shown in
Figure 1-6. Check Table 1-1 to be sure that you are using the correct cables with
your system configuration (the cables you use will be different depending on
whether you are using a bench system configuration—as shown in Figure
1-6—or a rack configuration).
Figure 1-6 Connect the Front Panel RF Cables
NOTE Steps 2 and 3 must be performed before you can use your network analyzer to
control the multiport test set.
2. Turn on the test set.
3. Turn on the analyzer and Press [System] -
87075 Setup - 87075 Control to
activate the test set control.