APC VT Power Supply User Manual


 
Operation – Operation Procedures
990-2282A-001 Smart-UPS® VT 10-40 kVA 400V, 208V, 200V – Operation 21
Restart – parallel system.
Warning
Only trained personnel familiar with the construction and the equipment may
restart the UPS system.
From the XR Enclosure(s) (if available):
Connect the batteries on the UPS units by
pushing them in.
From the UPS: Connect the batteries by
pushing them in.
From the XR Enclosure(s) (if available): Set
the DC disconnect switch (if available) to the
ON position.
From the external MBP: Turn all input
switches
(Q001) to position “1” (ON).
From the external MBP: Turn all output
switches
(Q002) to position “1” (ON).
From the external MBP: Turn the output
isolation breaker
(Q004) to position “1” (ON).
From the UPS: Turn load ON each of the UPS
units from the display via Control
Turn
Load on
Yes, turn Load on.
Check that the load is ON.
Note
The UPS system is now ready to support the load.
Note
Auto-detection on frequency – if a problem occurs call APC Customer Support (see the
back cover of this manual).