Dell 1500 Laptop User Manual


 
support.dell.com Rack Installation Guide 1-1
Dell™ PowerEdge™ 1550 and
PowerApp™ 120 Systems
Rack Installation Guide
This installation guide provides instructions for trained service technicians installing
one or more Dell
PowerEdge 1550 or Dell PowerApp 120 systems in a rack. This guide
includes procedures for the following three rack kits:
Two-post center-mount
Two-post flush-mount
Four-post rack cabinet
One rack kit is required for each system to be installed in the rack.
CAUTION: When installing multiple systems in a rack, complete all of the
procedures before attempting to install the next system.
Two-Post Center-Mount Rack Kit
Installation
This procedure provides instructions for installing a system in a two-post open-frame
relay rack, such as those found in telecommunications equipment facilities. Both
3-inch and 6-inch wide two-post racks are accommodated.
The two-post open-frame relay rack must be properly secured to the floor, to the
ceiling or upper wall, and where applicable, to adjacent racks, using floor and wall
fasteners and bracing specified or approved by the rack manufacturer or by industry
standards. Refer to the two-post open-frame relay rack manufacturer’s installation
documentation for precautionary warnings and information before attempting this
installation.
CAUTION: Do not attempt to install the system into a two-post open-frame
relay rack that has not been securely anchored in place. Damage to the
system and personal injury may result.