4.0 Installation
CAUTION: The GBC Voyager 3 can only be
installed by a trained GBC Service
Representative.
Before a Voayger 3 Laminator can be installed, there
are a few requirements that must be met. Make cer-
tain that each of the requirements listed in the fol-
lowing pre-installation checklist are met prior to
installation.
CA
UTION: Failure to follow the pre-installa-
tion check list can result in damage to the
laminator.
As a customer, you are responsible for ensuring the
crates are uncrated and the components are set in
proper position as illustrated in Figure 4.1.1
Suggested Floor Layout.The installation time is out-
lined to allow for maximum hands on training with
the operators.
4.1 Pre-installation
Are the doorways and hallways wide enough
for the laminator to be moved to the installa-
tion site?
Is there ample room for the laminator? The
laminator occupies 16 ft. by 6 ft. of floor space
(488 cm x 183 cm).
A safe work area constitutes enough room to
work with the materials at hand while being
free to move around the laminator without
interference from the laminator. You must
allow a minimum of 5 ft. (152 cm) in front of
the feeder and on the operator side, and a
minimum of 2 ft. (61 cm) behind the stacker
and drive side of the laminator. Refer to Figure
4.1.1 Floor layout.
Is the environment appropriate for the
laminator? A controlled environment is recom-
mended.
CA
UTION: The operating environment must
be free of dust, flammable liquids and
vapors.
The laminator requires a clean, dust and
vapor free environment to operate properly.
Operations Manual: Installation
Voyager 3
Voyager 3
2004 General Binding Corporation
Page 4-1