GE 20 Power Supply User Manual


 
g
GE
OPM_SGS_USM_10K_40K_0US_V010.doc 62/88 Operating Manual
SG Series
10, 20, 30 & 40 kVA
7.3.7 Restore to normal operation after “total off”
View of the panel after pressing the button total off.
All Contacts are open;
Rectifier
,
Inverter
and
Static-Switch
shutdown.
First operated unit All other units of the system
1. Reset total off by pressing and holding the “total off button and then the
inverter on
( I )
key, on any of the Units simultaneously, until Load is supplied
from Bypass and the Rectifiers start.
System output connects to Bypass Utility.
Rectifiers start with blinking LED.
At the end of Soft-start the LED’s remains lit.
The LCD screen
on all Units
shows LOAD ON BYPASS”.
FIRST OPERATED UNIT
All other units of the system
2. Connect the Battery to all Units by closing the external Battery Switches or
Fuses, in case of External Battery
.
Continue