Hardware options installation 97
o
For tower models, return the server to an upright position.
o For rack models, slide the server back into the rack.
23. Install the rack bezel (on page 25).
24. Power up the server (on page 22).
25. Do one of the following:
o For tower models, install the bezel ("Install the tower bezel" on page 23).
o For rack models, if removed, install the security bezel ("Security bezel option" on page 47).
Tower-to-rack conversion option
1. Back up the server data, and then record configuration information.
2. Close all applications, and then using the normal shutdown sequence, shut down the operating system.
3. Remove the bezel:
a. Unlock the tower bezel and then open the bezel door completely.
b. Slide the bezel up, removing it completely from the chassis.
c. Remove the two bezel snaps.
4. Press the Power On/Standby button.
The server powers down and enters standby mode. The system power LED changes from green to
amber. Power is still applied to the server.
5. Remove all power:
a. Disconnect each power cord from the power source.
b. Disconnect each power cord from the server.
6. Place the server on a flat, level work surface.