40 Planning the site
Developing the site
-
After selecting a site, the following items must be considered during site
development:
-
Space and equipment layout requirements
-
Equipment
rmrn
accessories
-
Detailed floor plans and loading requirements
-
Building cable plans
-
System wire routing
-
Cable termination points
The equipment room
Space and equipment layout requirements differ with each installation,
depending upon equipment selected and the available physical area. The
following categories of required space should be considered when planning
site needs:
-
Primary storage
-
Secondary storage
-
Maintenance/Technician area
Primary storage
The floor area required for an SL-1 depends on the number of columns of
UEMs
ordered, the length-to-width ratio of the area, and the location of
walls, partitions, windows, and doors. To determine the exact layout
required, prepare a detailed floor plan after reading all of the requirements
provided in this section.
Operating needs determine the location of free-standing peripherals like
printers and terminals. Printers and terminals must not exceed the
maximum distances defined for their interface circuits. Wall jacks and
outlets must be provided for all devices located in the equipment room.
Within a system there are certain requirements that must be met when
drawing up the equipment room floor plan.
Installation planning 553-3001-120