Sun Microsystems VSM GUI Computer Drive User Manual


 
312651601 Rev A Chapter 4 Installing Service Tapes for VSM GUI 31
FIGURE 4-1 JCL to Unload the VSM GUI Service Tape SMP/E JCL
Installing a Service Tape
Install the contents of a service tape using the following procedure.
1. Ensure that you have customized the installation jobs as described in “Set Up the
SMP/E Environment and Install the Software” on page 13.
2. If necessary, modify member
U1RCU.
If the cumulative service was downloaded from the StorageTek CRC, change the
SMPPTFIN and SMPHOLD DDs to point to the downloaded data set names. If it is a
physical tape, obtain the actual volume serial number “VT
yynn” from the tape cartridge
external label. If there was no HOLDDATA downloaded, then remove the SMPHOLD DD and
only receive
SYSMODS.
3. Run member
U1RCV to RECEIVE the VSM GUI service.
4. If necessary, modify member
U2APPLY.
Before running the apply job, review the output from the receive job for
HOLDDATA, and
follow the instructions given for each held PTF. When the requirements are met, bypass
the hold condition for that held PTF in the apply job with the
BYPASS parameter. Do not
bypass
HOLDERROR conditions.
5. Run member
U2APPLY to APPLY the VSM GUI service.
//jobcard JOB ‘accounting information’
//*
// EXEC PGM=IEBCOPY
//SYSPRINT DD SYSOUT=*
//SYSIN DD DUMMY
//*
//SYSUT1 DD DSN=SMPEJCL,DISP=(OLD,KEEP),
// UNIT=3480,
// LABEL=(3,SL,EXPDT=98000),VOL=SER=VTyynn
//*
//SYSUT2 DD DSN=hlq.SMPE.JCL,DISP=(,CATLG),
// UNIT=SYSALLDA,SPACE=(TRK,(10,2,10)),
// DCB=(RECFM=FB,LRECL=80,BLKSIZE=23440)
//*