Code Compliance
975-0046-01-01 1–5
Code Compliance
Governing installation codes vary depending on the location and type of
installation. Electrical installations must meet local and national wiring
codes. Installations of this equipment should only be performed by skilled
personnel such as qualified electricians and Certified Renewable Energy
(RE) System Installers. For a list of Xantrex Certified RE dealers, please
visit our website at www.XantrexREdealers.com.
Installation Tools and Materials
Tools Required The following tools may be required for installing this equipment.
Wire strippers
Assorted open-end wrenches or socket wrench and fittings
Torque wrench
Electrical tape
Multi meter (AC/DC volts, frequency)
Assorted Phillips screw drivers
3/16" Allen/Hex head driver
Slotted screw driver
Level
Pencil
Utility knife
Hardware /
Materials Required
The following materials may be required for completing this installation.
Conduits, bushings, and appropriate fittings for wire runs
Wire nuts
Electrical wire of appropriate size and length
Breaker Panels
Ground busses, bars, and/or rods
Six #10 wood screws or ¼ inch (6 mm) lag bolts and washers.
Important:
Be sure to obtain the appropriate permits, if necessary, prior
to starting this installation.