Wiring for On-Grid Applications Using Additional Circuit Breakers in the ACCB Only
975-0046-01-01 1–37
To make the hot connections:
1. Connect the factory-installed hot (black) wire from the Inverter Input
Breaker in the ACCB to the AC1 GRID terminal in the inverter
2. Connect the factory-installed hot wire (black) from the Inverter
Output Breaker in the ACCB to the INV OUT terminal in the inverter.
3. Connect the hot (black) wire from the main AC distribution panel to
the AC IN terminal in the ACCB.
4. Connect the hot (black) wire from the generator to the top of the
generator disconnect breaker in the ACCB.
5. Connect another hot (black) wire from the bottom of that same
generator disconnect breaker in the ACCB to the AC2 GEN terminal.
6. Connect a hot (black) wire from the AC OUT terminal in the ACCB
to the bottom of the additional circuit breaker installed in the ACCB
7. Connect another hot (black) wire from the top of that same additional
circuit breaker in the ACCB and route to the outlet that will be
supporting the AC load.
Figure 1-33
Hot Connections for an On-Grid Application Using Additional Circuit Breakers in
the ACCB Only
Additional AC Load
Circuit Breaker
1
3
2
4
5
6
7