Cisco Systems 4948E Switch User Manual


 
D-42
Catalyst 4948E and Catalyst 4948E-F Switch Installation Guide
OL-21561-02
Appendix D Regulatory Compliance and Safety Information
GR-1089-CORE Issue 3 Documentation Statements
GR-1089-CORE Issue 3 Documentation Statements
Statement 7016—GR-1089-Core Intrabuilding Lightning—Immunity
Requirements
Caution To comply with GR-1089-Core intrabuilding lightning-immunity requirements, you must use shielded
(screened) cable that is grounded at both ends.
GR-1089-CORE Issue 4 Documentation Statements
Statement 7001—ESD Mitigation
This equipment may be ESD sensitive. Always use an ESD ankle or wrist strap before handling
equipment. Connect the equipment end of the ESD strap to an unfinished surface of the equipment
chassis or to the ESD jack on the equipment if provided.
Statement 7005—Intra-building Lightning Surge and AC Power Fault
Warning
The intra-building port(s) of the equipment or subassembly is suitable for connection to intra-building
or unexposed wiring or cabling only. The intra-building port(s) of the equipment or subassembly
MUST NOT metallically connect to interfaces that connect to the OSP or its wiring. These interfaces
are designed for use as intra-building interfaces only (Type 2 or Type 4 ports as described in
GR-1089-CORE, Issue 4) and require isolation from the exposed OSP cabling. The addition of Primary
Protectors is not sufficient protection in order to connect these interfaces metallically to OSP wiring.
Statement 7012—Equipment Interfacing with AC Power Ports
This equipment shall be connected to AC mains provided with a surge protective device (SPD) at the
service equipment complying with NFPA 70, the National Electrical Code (NEC).
Statement 7013—Equipment Bonding Networks
This equipment is suitable for installations utilizing the Common Bonding Network (CBN).
Statement 7014—Installation Location
This equipment is suitable for installation in Network Telecommunications Facilities and locations
where the NEC applies.