Site Preparation Checklist
Ta b l e 2-2 Site Planning Checklist
Task No. Planning Activity Verified By Time Date
1 Space evaluation:
Space and layout
Floor covering
Impact and vibration
Lighting
Maintenance access
2 Environmental evaluation:
Ambient temperature
Humidity
Altitude
Atmospheric contamination
Airflow
3 Power evaluation:
Input power type
Power receptacles (Depends on power supply)
1
Receptacle proximity to the equipment
Dedicated (separate) circuits for redundant
power supplies
UPS for power failures
2
DC systems: Proper gauge wire and lugs
1. Verify that each power supply installed in the chassis has a dedicated AC source or DC source circuit.
2. Refer to the power supply’s kVA rating as a sizing criteria in determining the output required by the UPS. The power supply’s
kVA rating value is listed in the specifications table for each power supply in Appendix A.
4 Grounding evaluation:
Circuit breaker size
CO ground (AC- and DC-powered systems)
5 Cable and interface equipment evaluation:
Cable type
Connector type
Cable distance limitations
Interface equipment (transceivers)
6 EMI evaluation:
Distance limitations for signaling
Site wiring
RFI levels