C H A P T E R 2 Installing and Removing the Express Hub
15
3. Insert two pan-head screws with nylon washers through each
mounting bracket and into the rack.
4. Using a #2 Phillips screwdriver, tighten the screws to secure the
hub to the rack.
5. Continue with “Completing the Installation” to finish this
installation procedure.
Installing the Hub on a Table or Shelf
To install the hub on a table or shelf, follow these steps:
1. Install self-adhesive feet on the bottom of the hub.
Peel off the protective backing from the rubber feet and apply one
at each marked location on the bottom of the hub.
Feet placement
guides
4642
Attaching feet
2. Set the hub on a table or shelf so that it has at least 2 inches of
space on all sides.
3. Continue with “Completing the Installation” to finish this
installation procedure.
Completing the Installation
After you have installed the Express hub, connect power to the hub
and verify the installation.
To complete the installation of your Express hub, follow these steps:
1. Install any additional units in your stack (such as Express hubs).
For instructions on installing multiple hubs, see “Installing
Multiple Hubs” later in this chapter.
CAUTION
Do not connect the power
cords to the hubs until all the
units in the stack are installed
and hubs are connected by
cascade cables and are ready
for operation.