8.1 Unpacking
UnpacktheUPSindoorsonapavedoor.TheUPSshouldbeascloseaspossibletoitsnalstorage
location. Allow enough space for forklift operations to unpack the UPS crate. Then remove the crate.
Points to observe
• Retain all small articles during unpacking and installation.
• Make sure that exterior paint is not scratched and that the UPS cabinet is not damaged.
• DO NOT damage the UPS when using tools to remove packaging materials.
• If provided, DO NOT remove the plastic sheet cover, until installation.
• Do not remove the fan covers until UPS start up. The fan covers should be removed by factory
authorized personnel. Packing materials should be disposed by the appropriate means.
• Immediately report any abnormalities to Toshiba Customer Support Center or an authorized
representative.
8.2 UPS Clearance
Maintain the indicated clearance during installation. See Figure 8.1. Ensure that the front and top air vents
are NOT blocked.
FIGURE 8.1 - UPS CLEARANCE
Back 0 in. (0 mm)
Front
23 in.
(584 mm)
Top 12 in. (305 mm)