American Power Conversion 250 A Power Supply User Manual


 
Smart Distribution Panel with ATS
12 InfraStruXure Power Generation System
Front view, door open
Remove the dead front to
obtain access to the panel
board for maintenance and
wiring.
The Source 1 motorized
switch (see “Motorized
switches” on page 15)
controls operation of the
Source 1 input switch.
The automatic operation
control panel is used to set
the generator to automatic
operation or, alternatively, to
remove the generator from
automatic operation (see
“Automatic operation control
panel” on page 16).
The Source 1 lamp lights
green when the Source 1
switch is ON (closed).
The display interface
provides a local interface for
viewing status data,
configuring settings, and
operating the ATS. The
display interface has an LCD,
a five-button panel,
basic status lights, and a beeper (see “Display Interface” on page 29 for detailed information about the
contents and operation of each screen).
The sub-feed output breakers provide power to equipment in the data center (see page 68 for
detailed information about installing these breakers).
The Source 2 lamp lights green when the Source 2 switch is ON (closed).
The Source 2 motorized switch (see “Motorized switches” on page 15) controls operation of the
Source 2 input switch.
Use the latches to open the dead front.
pg0010c