Smart-UPS VT ® 10-40 kVA 380/400/415 V, 208/220 V, 200/208 V Battery Installation10
6. Insert the
interconnection plates
between the two
enclosures. One is
positioned toward the
front and the other
toward the rear. Note
how the “wings” on
the interconnection
plates rest in slots at
the top of the inner
panel on the XR
Battery Enclosure.
7. Align the two
enclosures and level
the three marked rows
of bolt holes in one
enclosure with the
holes in the adjacent
enclosure.
8. Push the two enclosures firmly together.
9. Bolt the two enclosures together by
using the six M6x25 mm screws and
nuts supplied in the kit: join one hole at
the front and one hole at the rear of the
enclosures on three levels.
10.Position the last and third U-shaped
floor anchoring bracket under the
adjacent enclosure (see previous
graphics) and insert a minimum of two
floor anchoring M8 screws (not
provided) through holes in the bottom
of the enclosure and through holes in
the U-shaped floor anchoring bracket,
and into the predrilled floor holes, and
then fasten the screws.
XR Battery Enclosure rear view
UPS rear view
UPS