APC 10-40 KVA 380/400/415 V Power Supply User Manual


 
Smart-UPS VT ® 10-40 kVA 380/400/415 V, 208/220 V, 200/208 V Battery Installation18
Connect Communication Cables
1. Feed the cable from pin connection J106 in the UPS down through the conduit (if appliccable).
2. Run the cable up into the XR conduit and connect it to pin connection J200 in the XR Battery
Enclosure.
3. If you use an XR2, run the cable from pin connection J204 in XR1 to pin connection J200 in
XR2.
BAT
BAT
UPS
XR