Powerware BD Switch User Manual


 
UPS Power Management
ConnectUPS Web/SNMP Card (X and BD Models) User’s Guide : Rev A www.powerware.com
24
6. To turn off the UPS and have it stay off (requiring
local interaction to turn it back on), change
Load
Segment to Restart following the return of AC Line
to NO.
If you want to effectively reboot the UPS and the
associated load, then set
Load Segment to Restart
following the return of AC Line
to YES and set Delay Before
Segment Restart
to a valid delay value to allow the UPS
to restart after the specified delay.
7. After choosing the desired values, select
Set Values to
update the card with the new information.
8. Select
Control from the ConnectUPS Web/SNMP Card
menuatthetopofthehomepageandselect
Load
Segment “ALL”
or the appropriate load segment
“NUMBER(S)”. Then select Turn UPS Off.
9. To initiate the shutdown sequence, select
Set Values
which instructs the ConnectUPS Web/SNMP Card to
send the appropriate information to the UPS and any
clients running the NetWatch client software.
Planning a Scheduled UPS Shutdown and Restart
You may use the ConnectUPS Web/SNMP Card to schedule
the day of the week and time of a shutdown and a startup. The
ability to schedule shutdowns and startups is UPS dependent
(consult your UPS documentation for more information).
1. Select
Configuration from the menu at the top of the
home page, then
UPS Shutdown Schedule.
2. Login as a Superuser.
3. You may configure up to seven event pairs. Enter the
upcoming
Shutdown Day and Shutdown Time,andif
needed, the
Restart Day and Restart Time. Times are in
24-hour format based on the date and time set within
the ConnectUPS Web/SNMP Card.
4. Click
Set Values to update the card.
5. Once the values are set, select
Control from the menu
at the top of the home page.