PANEL INSTALLATION
1. If applicable, remove optional rear cover of panel (four,
1
/4-20 hexhead bolts).
2. Decide if input cables will be fed from bottom-up or top-down.
NOTE
Panels are shipped from the factory for top-down input cable entrance to bay. If you intend to feed input cables from the bottom-
up, you must reverse the input terminal plates, as instructed in the following procedure.
If necessary, to change both input buses from top-down to bottom-up input cable entrance, refer to the following illustration and
proceed as follows:
a. Remove four,
3
/8-in. hex head cap screws securing each input bus assembly to panel.
b. Rotate this assembly for input bus A and resecure it where the bus B had been, and vice versa.
c. Torque bolts to 18 ft-lb (~24 N•m).