Cisco Systems OL-7822-06 Computer Drive User Manual


 
CHAPTER
6-1
Cisco Service Control Engine 1000 2xGBE Quick Start Guide
OL-7822-06
6
Completing the Installation
This module discusses how to verify link connectivity and how to install a Service Control application.
Examining the LEDs, page 6-1
Final Tests, page 6-1
Viewing Configuration, page 6-2
Saving the Configuration Settings, page 6-3
Examining the LEDs
The GBE Link LED must be green to verify that an active connection exists.
The GBE Rx and Tx LEDs (if flashing green) indicate that traffic is being received or transmitted by the
SCE 1000 platform, respectively.
Note that in an inline topology, the Rx and Tx LEDs indicate that packets are being received/transmitted
by the SCE 1000 platform.
In optical splitter topologies, the Rx LEDs are the sole indicators. The Tx LEDs do not “blink”, since
the Tx is not connected to the port in this topology.
Final Tests
The procedures for performing the final tests to verify that the SCE 1000 is functioning properly are
explained in the following sections.
Verifying Operational Status, page 6-1
Viewing the User Log Counters, page 6-2
Verifying Operational Status
After all the ports are connected, verify that the SCE 1000 is not in a Warning state.
To verify that the SCE 1000 is not in a warning state, complete the following steps:
Step 1 On the SCE 1000 Front panel, examine that the Status LED is flashing green.