36 Operating Manual BX600 S3
Installing the System in the Rack Installing the Hardware
© cognitas. Gesellschft für Technik-Dokumentation mbH 2009 Pfad: H:\April\PRIMERGY_Rebranding\von Walter\bx600_s3_ba\BX600S3_en\blade-us.k04
3rd-Party Rack
Certain framework conditions must be fulfilled:
– Installation dimensions (see the dimensions shown in figure 5 on page 37).
– Please ensure that the security mechanism (e.g. stopper or retention
system) on the server is working.
– The rack support uprights must allow the rails to be screwed on at the front.
– Frontally bolted rails.
The rails have with a linear alignment option to also allow adjustment to
different rack depths.
– No support for the cable management delivered with the mounting kit. This
cable management is customized for the Fujitsu Technology Solutions PRI-
MECENTER rack.
– Climatic conditions.
For the ventilation of the installed server, there must be sufficiently large
gaps for air intake at the front of the rack and air discharge at the back of the
rack.
1 rack front
2 rack rear
A rack depth (comparison PRIMECENTER rack 940/1000 mm)
B rack width (comparison PRIMECENTER rack 700 mm)
C clearance of the 19-inch installation level
C1 front 19-inch installation level
C2 rear 19-inch installation level
D area for cable routing (cable area depth) and ventilation
E area for front panel and ventilation
F right and left area for support systems
P PRIMERGY installation depth
a1 front left support upright
a2 front right support upright
b1 rear left support upright
b2 rear right support upright