HP (Hewlett-Packard) FC 1GB/2GB SWITCH 16B Switch User Manual


 
HP Surestore FC 1Gb/2Gb Switch 16B Installation and Reference Guide 2-7
Installing and Configuring the HP Surestore FC 1Gb/2Gb Switch 16B
2
5. Assemble the outer rails by completing the following steps:
a. As an aid in assembly, two rubber washers have been included to help keep the rear
slotted portion of the outer rail flush against the rear rail-tray brackets. Install them
as shown in Figure 2-6.
Figure 2-6. Installing the Rubber Washers
b. Insert the alignment pins attached to the outer rail front flange into the center opening
in the rack.
Note For the Compaq/Rittal rack, the alignment pins will be resting on the top
surfaces of the spacers.
c. Depending on the rack you are using, complete one of the following tasks:
For an HP rack, install one M5 Torx screw in the upper hole location of the right
rail. Then, install one M5 Torx screw in the lower location of the left rail. See
Figure 2-7.
Figure 2-7. Assembling the Outer Rails (HP Rack)
For a Compaq/Rittal rack, install one #10-32 x 5/8 Phillips pan-head screw in
the upper hole location of the right rail. Then, install one #10-32 x 5/8 Phillips
pan-head screw in the lower location of the left rail.