2
INSTALLING THE
FMS 100-TX H
UB
This chapter discusses the following topics:
■ Unpacking the hub
■ Positioning the hub
■ Installing the hub
■ Installing the transceiver interface modules
■ Using the Redundant Power System
■ Replacing the fuse
Unpacking the
Hub
When unpacking the hub, follow these steps:
1 Open the shipping container and carefully remove its contents.
2 Return all packing materials to the shipping container and save it.
If the hub must be returned, ship it in its original shipping container (or one
providing equivalent protection), or the warranty will be voided.
3 Verify that you have received all items that are shipped with the hub, as
listed below.
4 Inspect each item for damage. If you find any omissions or damage, contact
your network supplier and the carrier that delivered the package.
Each LinkBuilder FMS 100-TX hub is shipped with the following:
■ Rack mounting kit containing two brackets and four screws
■ Four rubber feet for desktop placement
■ AC power cord