American Power Conversion SYMSTRF3I Power Supply User Manual


 
Start-Up Procedure - Page 1
990-7167-001
Star tup Procedure
After the electrical wiring connections are verified, power and battery modules can be installed and the Symmetra
TM
can begin to deliver conditioned power to the output power panel(s).
Securing The Frame - Setting The Leveling Feet
1. Locate the frame in its final operating position.
Note: Leave a minimum of 12” (30 cm) of clearance at the rear of the frame for adequate airflow. Make sure the
system enable switch remains accessible.
2. Hand turn all four leveling feet until the pads make contact with the floor.
3. Use a wrench to extend each leveling foot by turning the hex nut two complete turns.
4. Adjust the leveling feet until the frame is level front to back and side to side.
Lower all four leveling feet
n After the leveling feet are lowered, attempting to move the frame may bend them.
Notice!