NEC 151944 Network Hardware User Manual


 
CHAPTER 3 ND-46550 (E)
Page 16
Revision 2.0
2. INSTALLATION PROCEDURE
Install the Remote PIM System according to the following procedure. Figure 3-3 and Figure 3-4 show the
installation procedure for the main site and the remote site.
Figure 3-3 Installation Procedure for Main Site
Switch Setting of DAIA Card
START
Mounting of DAIA Card
Note: For the main site, this manual describes only the installation procedure exclusively required for the
Remote PIM System. Refer to the Installation Procedure Manual for regular installation.
See Section 2.1.1
See Section 2.1.2
Switch Setting of DAIC Card
See Section 2.1.3
Mounting of DAIC Card
Connection Between
Main Site and Remote Site
BUS Cable Connection
END
Mounting of BS00 Card
See
Installation Procedure Manual
* These procedures are required even if the main
site is 1-PIM configuration.
Mounting of CP01 Card
and
Circuit Card Manual
.
See Section 2.1.5
See Section 2.3
MP Reset
See Section 2.4
See Section 2.1.4