NEC 151944 Network Hardware User Manual


 
ND-46550 (E) CHAPTER 3
Page 65
Revision 2.0
2.3.2 DTI Connection at Remote Site
Connect the cable to a CSU or directly to the Main PIM via the CN connector on the DAIB/DAIC card as shown
in Figure 3-40. Connection of DAIC cards between the Main PIM and the Remote PIM is available in the same
manner as the DAIA-DAIB connection.
Figure 3-40 DTI Cable Connection via CN Connector (Remote Site)
REMOTE PIM
CSU
MDF
TWISTED-PAIR
CABLE
DAIB/
BWB
(SHIELD TYPE)
MAX. 656 ft. (200 m)
CN
DAIB/DAIC MDF
CN
TB
TA
RB
RA
TO CSU/MAIN PIM
SEND
RECEIVE
4
3
2
1
BA1
AA1
BA0
AA0
TB
TA
RB
RA
CN CONNECTOR
(0.65Φ cable)
Note: When the Remote PIM is directly connected without CSU, maximum distance is
1312 ft. (400 m) between the Main PIM and the Remote PIM.
Note
DAIC