Sun Microsystems 2500 Computer Drive User Manual


 
26 Sun StorageTek 2500 Series Array Hardware Installation Guide March 2007
Two 6-meter RJ45 -RJ45 Ethernet cables (one per controller module)
One RJ45-DIN9 cable
One RJ45-DB9 adapter
Sun StorageTek Common Array Manager Software CD
Sun StorageTek Common Array Manager Software Installation Guide (on the
software CD)
Common Array Manager sscs CLI Quick Reference Card
Sun StorageTek 2500 Series Array Hardware Installation Guide (Hardcopy)
Accessing Documentation guide
Premium feature license cards (ordered optionally)
Ship kit for each expansion tray
Two 1-meter copper SAS cables (one per I/O module)
Accessing Documentation guide
AC power cords are shipped separately with each tray.
Preparing the Cabinet
Select the cabinet in which you will be installing the array. Be sure the cabinet is
installed as described in the installation instructions provided with it.
1. Stabilize the cabinet as described in the cabinet documentation.
2. If the cabinet has casters, make sure the casters are locked to prevent the
cabinet from rolling.
3. Remove or open the front panel.
4. Remove or open the vented back panel.
Planning the Order of the Tray Installation
Install the trays starting with the controller tray at the lowest available 2RU tray slot
in the cabinet. Next, install the expansion trays for the first controller tray. If room
remains in the cabinet, repeat for the next controller and expansion trays.
Starting at the bottom distributes the weight correctly in the cabinet.