APC G35T10KF1B2S Power Supply User Manual


 
Install XR Battery Enclosures (Option)
Remove the Cable Landing Cover and Bottom Plates
WARNING: Before carrying out the steps below, the system must be in total power
off and the batteries must be removed.
To access the cable landing area in the UPS and the XR Battery Enclosure(s), follow this procedure:
1
4
3
2
1
4
3
2
XR Battery Enclosure UPS
1. Loosen the six M4 screws from the cable landing cover plate on the UPS and the XR Battery
Enclosure(s) and then remove the plates.
2. In installations with busbar connections, remove the screws from the bottom plate on the UPS
and the XR Battery Enclosure(s) and then remove the plates.
3. Punch holes in the bottom of the conduit boxes to t the size of the conduit pipes.
4. Attach the bottom part of the conduit boxes to the back of the UPS and to the back of the XR
Battery Enclosure with four screws each (if applicable).