APC G35T10KF1B2S Power Supply User Manual


 
Install Seismic Option
Install the Seismic Battery Lock
Note: In seismic areas, dispose of the battery securing brackets that were used to secure the
batteries during transport and use the seismic battery locks to secure the batteries.
Required parts:
Four battery locks and 12 M5 screws for narrow
battery enclosures.
Six battery locks and 30 M5 screws for wide
battery enclosures.
1. Place the battery lock below the battery row.
2. Secure the battery lock by the provided M5
screws.
Install the Seismic Stabilizing Brackets
Required parts:
UPS, Battery Enclosure and Transformer
Eight 10 mm ttings
18 M6 nut washers
One horizontal bracket
Four stabilizing brackets
Maintenance Bypass Panel (MBP)
Eight 2 mm ttings
18 M6 nut washers
One horizontal bracket
Four stabilizing brackets
42
MGE™ Galaxy™ 3500 10-30 kVA 208/220 V Single and Parallel Installation
990-1957C-001