Prepare for Cables
Remove the Batteries
Note: See “Remove the Battery Modules“ for information on how to remove the batteries.
Run the Communication Cables
Three different ways of routing cables
Note: The enclosures in a parallel system can be kept apart, or they can be assembled with
interconnection plates. If the enclosures are kept apart, the communication cables can be run
in conduits (if applicable).
The routing of cables between the UPS units can be done in three different ways.
• UPS units apart (without conduits and without interconnection plates)
• UPS units bayed together (without conduits and with interconnection plates)
• UPS units apart or bayed together (with conduits and optional interconnection plates)
990-1957C-001
MGE™ Galaxy™ 3500 10-30 kVA 208/220 V Single and Parallel Installation
37